Custom Mahjong Launch Timeline: When to Order

Your launch date is fixed. Work back from it through transit, production and the sample to find the latest day to send the brief.

Gloved hand placing custom engraved acrylic mahjong tiles into colored acrylic racks on a factory packing bench, with export cartons and a planning calendar behind

The calendar covers the holiday season first, then Chinese New Year and spring launches, using the lead times published on our process page.

Key Takeaways

  1. Plan backward: arrival date minus transit, production, your sample review, sample courier, sample making and proof gives the latest brief date.
  2. Published estimates: one complete sample set takes about 25–30 days to make, and production takes about 30 days after sample approval for every quantity.
  3. Transit after dispatch is about 30 days by sea or 10–12 days by air. From brief to arrival, plan roughly 80–90 days by air and 100–110 by sea.
  4. For Christmas arrival by air, send a complete brief by late September; an early-November brief lands around late January by air.
  5. For a spring or Mother's Day launch, get the sample approved before Chinese New Year (February 6, 2027) so production starts as soon as lines restart.
On this page
  1. Work backward from the date the sets must arrive
  2. A worked example: 100 sets briefed on November 3
  3. What pushes the date out
  4. Chinese New Year: finish the sample before the holiday
  5. Spring and Mother’s Day launches
  6. The fast path: a sample that is already approved
  7. Copy this timeline into your brief

Work backward from the date the sets must arrive

A custom mahjong launch timeline starts at the arrival date and subtracts each stage: transit, production, your sample review, sample courier, sample making, then the quote and proof. What remains is the latest day to send a complete brief. Each stage has a published planning estimate, and two of them are yours to control.

The formula is simple enough to keep on one line:

Latest brief date = arrival date − transit − production − your sample review − sample courier − sample making − quote and proof.

The order of these stages is fixed because production starts only after you approve one complete physical sample set. The stages, with the estimates our custom mahjong set production process page publishes:

StagePlanning estimateWho controls it
QuoteWithin 24 hours of a complete briefUs, once the brief is complete
Digital proofDepends on artwork and revision roundsMostly you
Sample makingAbout 25–30 days after payment and proof approvalUs
Sample courierExpress, about 5–7 days after dispatchCarrier
Sample reviewYour decisionYou
Production, any quantityAbout 30 days after sample approvalUs
Inspection and packingInside the production windowUs
Transit after dispatchSea about 30 days, air about 10–12Carrier and customs

Transit estimates exclude production and depend on the route, customs and final delivery, so the quote confirms the service and the arrival estimate for your address. The mahjong freight estimator gives a planning budget for each shipping method before you ask.

A worked example: 100 sets briefed on November 3

A brand that sends a complete brief for 100 custom American mahjong sets on November 3, with finished vector artwork, has sets ex-factory around January 18 in this example, before the Chinese New Year shutdown. They arrive around January 30 by air or February 17 by sea.

The example uses the published estimates plus two assumptions you can change: about six days for the quote, proof and sample invoice, and three days for your own sample review.

StepDaysRunning date
Brief sent0November 3
Quote, proof approved, sample invoice paid6November 9
Sample made (upper estimate)30December 9
Sample delivered by express7December 16
Your review and approval3December 19
Production of 100 sets, including inspection and packing30January 18
Arrival by air (upper estimate)12January 30
Arrival by sea30February 17

Production is about 30 days for every quantity, so a larger run follows the same calendar; packing and freight booking for big runs are confirmed per order. A split plan, with a launch portion by air and the balance by sea, is assessed per order once we know the quantity needed first and the destination.

What pushes the date out

Four things move a mahjong launch date more than quantity does: late color changes, artwork that fails the file check, extra proof or sample rounds, and choosing sea over air. Each one lands before production, so the delay carries straight through to the arrival date.

  • Color changes. Every tile-body color is made to order inside the 25–30 day sample, so pick colors from the color reference board or send Pantone targets before sampling. A color change after the sample can mean another sample.
  • Artwork. Custom engraved faces need outlined vector artwork with linked assets included. We manufacture from your finished files and do not redraw or vectorize. The artwork-to-production guide explains what a production-ready file looks like.
  • Revisions. A change to size, layers or artwork after the sample can mean another proof or another sample. Confirm the revised scope, cost and timing before you plan around it.
  • Packaging. Standard shrink-wrap export packaging is included. Printed boxes start at 500 pieces per design, so a holiday gift box for a 100-set run is a separate decision with its own minimum.

Payment timing matters too. Production orders of USD 3,000 or less are paid in full before production; above that, a 40% deposit starts production and the 60% balance is due before shipment. A payment that waits a week moves the whole calendar by a week.

Chinese New Year: finish the sample before the holiday

Chinese New Year 2027 falls on Saturday, February 6, with the national public holiday running February 5–8.1 Factories, packaging suppliers and freight slow for several weeks around it, so treat late January through late February as a gap in any production calendar. A sample approved before the holiday lets production start as soon as lines restart.

Two briefs, two outcomes, using the same 100-set assumptions:

Brief sentSample approvedEx-factoryAir arrivalSea arrival
November 3, 2026About December 19About January 18About January 30 (air)About February 17
December 1, 2026 (production crosses the holiday, about 14 days added)About January 16About March 1About March 13 (air)About March 31

An early-November brief finishes production before the holiday. A December brief puts the production run across the shutdown. Our Chinese New Year ordering calendar covers the factory pause, restart and freight booking in more detail.

Spring and Mother’s Day launches

Mother’s Day 2027 in the United States is Sunday, May 9. A brand that wants 100 custom sets in its warehouse by mid-April should send the brief by early December at the latest, and by early November if it wants production finished before Chinese New Year. Anything later depends on air freight.

Spring is the season where the holiday gap does the most damage, because a sample started in January runs into the shutdown. Briefing in early November gives you a sample in hand before the holiday, time to approve it calmly, and production finished before lines stop.

The fast path: a sample that is already approved

The quickest custom mahjong order is one whose sample is already approved. A repeat order or a second run of an approved design starts at production, which removes about five to six weeks of sample making, courier and review from the calendar. Rush dates are confirmed in writing per order, not offered as a standard lead time.

Our 14-day trade-show order shows the pattern: 50 custom sets left the factory 14 days after release because the sample was already signed off. If you plan several launches a year, approve the sample for the next design while the current run is in production, so the next launch only waits on production and transit.

For a first order, the sample stage cannot be skipped. One complete custom set costs USD 500 including courier, is paid separately and is never credited to production. Production minimums are 50 complete sets per tile design. The sample stage page lists what the sample includes and when its clock starts.

Copy this timeline into your brief

Send the arrival date with the brief, not after the quote. A complete brief lets us check the schedule along with the price and tell you in the first reply whether the date works, needs air, or needs a smaller first shipment. Use the configurator to fill the brief and add the date there.

Include these items:

  1. Quantity per design (production starts at 50 complete sets per tile design).
  2. Tile count, size and layers, face process and artwork status.
  3. Sheet colors from the stock board, or Pantone targets if you accept the longer schedule.
  4. Accessories and packaging, with their own minimums.
  5. Destination address or port, shipping term and preferred shipping method.
  6. The date the sets must arrive, and whether part of the order is needed first.

When you are ready, design your own mahjong set in the configurator and send the brief with your launch date. The manufacturing cost guide helps you compare FOB and delivered budgets for each shipping method.

Footnotes

  1. Office Holidays: Chinese New Year in China — lists Chinese New Year 2027 on February 6 with public holidays on February 5–8, 2027. ↩

Share this guide

Frequently Asked Questions

When is the last day to order custom mahjong sets for Christmas?

Work it out from your arrival date. With finished artwork, 100 sets take about 76 days from brief to ex-factory in our planning example, then about 10–12 days by air or about 30 by sea. For arrival around December 21 by air, send the brief by late September; by sea, by early September.

Does the timeline change if I order more sets?

Yes. Production is about 30 days after sample approval, for every quantity. The sample stage stays the same. Other quantities and the start date are confirmed on your quote.

Can I skip the sample to save time?

No. Production starts after you approve one complete physical sample set, USD 500 including courier, paid separately and never credited. The fastest path is a repeat order or a design whose sample is already approved: our 14-day trade-show order shipped 50 sets because the sample was already signed off.

Do custom sheet colors add time?

No. Every tile-body color is made to order and is already included in the 25–30 day sample. A color change after the sample is approved can mean another sample, so settle colors before sampling.

Do printed gift boxes fit a 50-set holiday order?

Printed boxes start at 500 pieces per design, so a 50- or 100-set order ships in the included standard export packaging. Plan printed packaging as a separate decision with its own minimum.

Send Your Launch Date With the Brief

Tell us the quantity per design, set specification, artwork status, destination and the date the sets must arrive. We reply within 24 hours with the schedule that date allows.